Platform construction under special conditions - Dorfgastein & Bad Hofgastein in focus
.webp)
Construction activities
As part of the modernization of the Tauern line, the Dorfgastein and Bad Hofgastein railroad stations are currently the focus of intensive construction activity. The focus is on the construction and renovation of the platform facilities - a key element for safety, accessibility and comfort in rail operations.
Platform construction despite high groundwater levels
At Dorfgastein station, the high groundwater table posed a particular technical challenge. In order to create the conditions for the construction of the new platform, the jet grouting method (DSV) was used - a method for improving the subsoil in which cement suspension is injected into the ground using high pressure. This measure was used to secure the excavation pit for a stable and dry construction pit.
.webp)
Bad Hofgastein: Barrier-free platform access completed
Work is also progressing according to plan in Bad Hofgastein. The barrier-free access to the main platform has already been completed - a visible sign of the successful implementation of the modernization measures. Further work at the station is also consistently geared towards the requirements of modern, user-friendly railroad infrastructure.
.webp)
Modernization of the platforms
The construction of platforms combines numerous specialist areas: Ground engineering, structural engineering, traffic and safety requirements as well as integration into ongoing rail operations. Together, they create modern interfaces between rail and passengers - robust, safe and future-proof.
.webp)
Realization in a joint venture with the Stoik office
Both projects are being realized in collaboration with Büro Stoik (ARGE TM3-STOIK). The partnership-based cooperation enables efficient and high-quality implementation of the measures - even under challenging conditions.
Special thanks go to all those involved in the project, whose expertise and commitment have made a significant contribution to the success of these projects
More news
Company outing in Salzburg's Pongau region
%2520(1620%2520%25C3%2597%25201620%2520px)%2520(1).webp)
Company outing in Salzburg's Pongau region
Success at the Wien Energie Business Run 2023

Success at the Wien Energie Business Run 2023
Platform construction under special conditions - Dorfgastein & Bad Hofgastein in focus

More news
Company outing in Salzburg's Pongau region
%2520(1620%2520%25C3%2597%25201620%2520px)%2520(1).webp)
Company outing in Salzburg's Pongau region
Success at the Wien Energie Business Run 2023

Success at the Wien Energie Business Run 2023
Platform construction under special conditions - Dorfgastein & Bad Hofgastein in focus

05.05.2025
Further updates
Structural work on the DANI2 maintenance hall completed
%2520(1440%2520x%25201440%2520px).webp)
Structural work on the DANI2 maintenance hall completed
Structural work on the DANI2 maintenance hall completed
Work is in full swing in the Dosto maintenance hall New ÖBB Floridsdorf